CDA prepares PC-1 to build Sihala-Kahuta road fly over

0
2

Islamabad : Capital Development Authority (CDA) has prepared PC-1 to build fly over across SAHALA- KAHUTA road .
This fly over will be built on railway line of SAHALA- KAHUTA road.
The PC1 of fly-over has been sent to interior ministry for approval. This over head bridge will be built in the direction of KAAK Bridge to KAHUTA at the distance of 6 kilometer over railway track.
According to PC1 of SALALA-KAHUTA fly over the total cost will be 483.00 million rupees whereas the length of fly over is 1800 ft and the length of road will be 900 ft.
The time of completion fly over on SAHALA- KAHUTA road will be 12 months whereas the cost of construction of project will be provided under public sector development programme (PSDP).
It was the old standing demand of residents of the area to build fly over because of the traffic problems on SAHALA- KAHUTA road.